Glenview Park District Strategic Plan

Setting Priorities for the Future


Following a period of rapid growth between 1990 and 2005, the Glenview Park District board and staff in 2006 developed a Strategic Plan for 2007-2010 to set future priorities for the park district. Prior to developing the plan, the park district surveyed 5,000 residents and conducted several focus groups to identify possible priority areas. Employee teams then developed recommendations to address each area. These recommendations were reviewed and prioritized at a series of meetings in October 2006 by a Strategic Plan Advisory Committee (SPAC) consisting of board members, senior staff and residents. Their feedback and prioritization of these recommendations became the basis for the Glenview Park District Strategic Plan for 2007-2010 which was approved by the park board in January 2007. To review a copy of the entire Strategic Plan, click image above.

Strategic Plan Initiatives
Below are the initiatives outlined in the Strategic Plan and the progress which has been made toward accomplishing these tasks as of September 2008. Entries in red denote accomplishments made since previous update in April 2008.


Initiative Status Code
+ Completed
* Started
  = Not Started
HOLD On hold

 

Initiative: UPGRADE EXISTING FACILITIES *
Item Status Initiative Target Date Comments
1.1 + Develop a plan and funding for the ongoing repair and maintenance of existing facilities. 2007-2010 Capital replacement and a multi-year plan for the use of developer donation funds are in place.
1.1A = Hire a firm to conduct a facilities-condition analysis to document and plan for short-term and long-term needs based on the lifecycle of each building. 2007-2008 Gathering information on potential consultants.
1.1B = Develop uniform maintenance standards 2008-2009  
1.1C * Develop a facilities maintenance system for tracking assets, work requests, parts inventory, labor and preventive maintenance schedules. 2008-2009 Installed Rec Trac upgrade which has capability to handle some of these aspects.
1.1D * Implement a method for remote monitoring of mechanical systems to troubleshoot and monitor system performance and adjust levels of operation for energy conservation 2008-2009 Implemented KMC Controls at Park Center for mechanical systems and implemented remote monitoring of computer servers. The new Ice Center mechanicals have the capability for some level of remote monitoring but this is still being investigated.
1.1E = Develop a master plan and funding for annual fieldhouse maintenance and/or replacement 2008-2009  
1.2 * Centralize management responsibility for custodial services, mechanical systems/ maintenance repairs, building supplies procurement/ inventory and energy management contracts. 2007-2008 Joint custodial bid has been completed. The Cooperative Purchase Program from IPRA is centrally managed through the Recreation Division.
1.3 + Conduct a trend analysis and develop projections for program participation levels to drive future facility renovation and development. 2007-2008 Registration and Attendance report has been developed which provides the basis for ongoing analysis. The second year report (2007-2008 fiscal year) was presented to park board in Sept. 2008.
1.4 + Develop a master plan for the Town and Country property which includes a park maintenance facility and athletic fields. 2007-2008 Plan developed and approved by the park board.
1.5
* Conduct a needs assessment of community sports organizations using park district athletic fields to drive future development/ renovation of sports fields 2007-2008 Initial staff assessment is complete and was used to help with Community Park West II planning.
1.6 * Work with local sports organizations to more forward on the development of new fields that can be funded through grants and donations. 2008-2009 New baseball fields developed at Community Park West II with assistance from Glenview Youth Baseball.
1.7 * Update/develop plan to meet ADA requirements 2009-2010 All renovation projects include ADA compliance features.
2.1
+ Renovate ice skating mechanical systems 2007-2009 Project completed on target. Renovated facility opened Sept. 2, 2008.
2.1A + Develop construction plans for Ice Center mechanicals 2007-2008 Plans are done; construction scheduled.
2.1B + Begin construction on Ice Center mechanicals 2008-2009 Project completed on target. Renovated facility opened Sept. 2, 2008.
2.2
*
Plan and move forward on funding for efficient office facilities for Park District administration 2007-2009 Concept approved by Board. Intergovernmental agreement has been approved by both elected boards. Staff representatives from each agency have been assigned to the project and initial planning meetings are underway.
2.2A * Develop construction plans for administrative offices 2008-2009 Date changed from 2007-2008. Space needs have been identified.
2.2B = Begin construction on administrative offices 2009-2010 Date changed from 2008-2009. Anticipate construction to begin Fall 2009.
2.3 * Plan and move forward on funding for an efficient Park Services maintenance facility 2007-2008 Plan to move forward with construction drawings approved by park board in July 2008.
2.3A + Evaluate the feasibility of including next phase of Community Park West Athletic Field development with the project. 2007-2008 Athletic fields are in CPW master plan.
2.3B
+ Develop construction plans for Park Services maintenance facility 2007-2008 Board approved preparation of construction drawings in July 2008.
2.3C = Begin construction for Park Services maintenance facility 2009-2010 On target to begin construction in summer 2009.
2.4 * Enhance and increase the amount of natural resource areas 2007-2008 Took over Air Station Prairie; Gallery Park planned for 2008; new berm and native prairie being planned at The Grove as part of tollway project. Will explore other opportunities as they become available.
2.4A * Work with the Natural Resource Commission and other entities to develop an updated inventory of natural areas and open space. 2007-2008 Working with VOG contractor on the inventory.
2.4B + Updated Glenview Park District environmental policies 2008-2009 Board approved in August 2008.
2.4C * Implement an Environmental Management Plan 2007-2010 Environmental Team is in place, initial training complete; plans are being developed.
2.5 Hold Construct a third sheet of ice at the Glenview Ice Center if funding becomes available. Hold
Need funding
We will continue to explore the land adjacent to the facility and funding opportunities and monitor market demand.
2.6 = Develop a plan for the construction of a permanent clubhouse at Glenview National 9 and implement 2009-2010  
2.7 * Explore grant and donation opportunities. 2007-2010 Applied for grants or Legislative Line-items for Wagner Farm, Glenview Ice, Crowley, CPW, tennis lighting, road work at The Grove.
2.7A * Replace switches and reconfigure lighting in Park Center public areas and pool. 2007-2010 Design is complete. Bid process is schedule for November 2008. Decision to proceed with this improvement will depend on cost of other priorities.
2.7B + Replace lighting at Glenview Tennis Club 2007-2010 Lighting has been installed. Grant application submitted. Savings of $5,000-$8,000 projected.
2.7C + Replace lighting and emissivity ceiling at Glenview Ice Center 2007-2010 Part of the overall Ice Center renovation project completed September 2, 2008.
2.8 * Develop a master plan for a dog park and construct if a site and funding becomes available. 2007-2010 Master plan approved by Board. Bid process is complete. Construction began in Spring/Summer 2008 and is 30% complete.
2.9 + Complete office renovation at The Grove 2007-2008  
2.10 + Replace the Crowley Park Fieldhouse 2007-2008 Completed. Re-dedication ceremony conducted in June 2008.

* For additional information on how these project were prioritized and their associated costs, click here.


Initiative: STRENGTHEN OPERATIONAL AND LONG-TERM FINANCES

Item Status Initiative Target Date Comments
3.1
+
Finalize and approve Categories of Park Services and District Financial plan.
2007-2008
Complete- Board approved.
3.2
+
Develop/update a set of financial policies to guide decision making (use of TIF, use of rollover bonds, allocation methodology of G&A, bond refinancing guidelines, fund balance goals, etc.).
2007-2009
Financial plan has been approved by the Board for the use of TIF and rollover bonds.
3.3
*
Increase the use of financial analysis in business planning (end of TIF, debt levels, revision of management reports).
2007-2009
Reports have been developed on key indicators for retail operations, reports for recreation program profit/loss have been modified; working on financial aspects for facility business plans. Financial Plan for capital projects and use of TIF has been developed.
3.4
*
Develop business plans for each major program area predicated on the “Categories of Park Services” parameters.
2007-2009
See specific results for functional areas below.
3.4A1
+
Develop and implement Glenview National 9 business plan.
2007-2008
Complete
3.4A2
*
Develop and implement Glenview Park Golf business plan.
2007-2008
Working with the facility management, accounting and marketing to develop plans.
3.4B
=
Develop and implement Tennis business plan
2009-2010
Date changed from 2008-2009 based on prioritization of projects.
3.4C1
+
Develop and implement Ice Center business plan
2007-2008
Complete
3.4D
*
Develop and implement Fitness business plan
2008-2009
Will be part of annual recommendation scheduled for Dec. 2008.
3.4E
+
Develop and implement Aquatics business plan
2007-2008
Complete
3.4F
=
Develop and implement Recreation business plan
2009-2010
 
3.4G
=
Develop and implement Food Service business plan
2008-2009
 
3.5
+
Develop a plan to increase facility reserves.
2007-2008
Increases in reserves were planned for in 2007-2008 budget for Recreation, Park Services, Farm and Fields and Museum funds.
3.6
*
Evaluate, update and improve internal financial processes and controls (i.e. purchasing controls, cash handling processes and controls, purchase order processes, etc.).
2007-2009
Controls have been tightened on supporting documentation for purchases, payment of sales tax, use of Get-It card.
3.6A
*
Update purchasing policies
Purchasing policy has been developed and reviewed by our auditors. Reviewed by park board Finance committee and passed at September board meeting. Retraining of all staff will take place in October.
3.7
+
Attain GFOA Certificate of Excellence in Financial Reporting
2007-2009
Received in both 2007 and 2008.

Initiative: STRENGTHEN COMMUNITY RELATIONSHIPS
Item Status Initiative Target Date Comments
4.1 * Investigate the feasibility of a cooperative agreement with the Village of Glenview for the operation and management of Gallery Park 2008-2009 Moved to 2008-2009. decision was made to put on hold until Tyner had been operational for one year. Initial discussions have taken place and additional discussion will continue in Fall 2008.
4.2 + Assist Village in planning best use for Navy property TBD by Village Ongoing discussions with Village, School District and Park District on the public use land.
4.3 + Investigate feasibility of a cooperative agreement with the Village of Glenview for the operation and management of Air Station Prairie and Tyner Interpretive Center 2007-2008 Transition of operation and management complete.
4.4 * Re-evaluate and update school/park agreements 2007-2009 In process of gathering school usage data.
4.5
*
Develop formal partnership agreements with affiliates and partners in the delivery of recreation programs to the community (AYSO, GYB, GYSA, Junior Titan Football, Titan Girls Softball, etc.)
2007-2009
Originally a 2008 item; Finalizing cooperative agreement with GYB for development of 4 fields at CPW; Exploring cooperative efforts with GBS for their new fitness center; negotiating a land swap with GBS and Glenview Ice Center for better usage of public land. Rewrite of recognized organization policy is scheduled for fourth quarter of 2008. Working closely with District 225 on GTAC program and future pool use.
4.6 * Develop and implement a communication plan to residents on the many benefits of new cooperative efforts with Village and affiliates 2007-2009 Ongoing project; have publicized Tyner award, senior gift to school district.
4.7 * Explore cooperative efforts with Village related to the development of proposed maintenance facility at Community Park West 2007-2008 Have worked cooperatively with the VOG on a temporary road at CPW, snow dumping and salt storage issues.
4.8 * Conduct regular meetings with affiliated sports organizations to aid in the planning and delivery of services 2007-2009 Staff liaisons attend regular Board meetings for AYSO and GYB, part of CPW II planning. Visitation meetings planned for Fall 2008.
4.9 * Explore opportunities to work cooperatively with the Village to meet community needs 2007-2010 Used Park Center as emergency Red Cross center during severe storm; Worked cooperatively on storm clean-up and sandbagging efforts; joint efforts to create temporary road through CPW during bridge construction.

Initiative: SUSTAIN HIGH QUALITY PROGRAMMING
Item Status Initiative Target Date Comments
5.1 * Develop and maintain a District-wide, facility by facility electronic web-based calendar available to all program staff for use in scheduling staff and to assist in avoiding other District major events. 2008-2009 New calendar is on the website that is updated weekly.
5.2 * Review and update the methodology for addressing facility overhead when determining program pricing using the “Categories of Park Services” guidelines. 2007-2008 Will be part of financial policies currently being developed.
5.3 = Create and implement a standardized (District-wide) evaluation form and process to gather information from current participants regarding interests, fee levels, time and day preferences. 2008-2009  
5.4 = Evaluate and maximize the use of school and other public space as may be available in the community in order to expand programmable space. 2009-2010  
5.5 * Conduct a program audit/analysis and expand programs where needed with special emphasis for specific populations in community (teens, ethnic, economic, single/working parents, etc.) 2007-2010 Conducted 27 new programs during first year of operation at Air Station Prairie; Co-sponsor of Our Climate Matters; new special events at Wagner Farm and outdoor pools; Took over and enhanced Farmer's Market.
5.6 = Update the policies and procedures governing recognized organization status of smaller affiliated groups such as neighborhood associations, clubs, non-profit special interest groups. 2009-2010  
5.7 * Explore opportunities to expand amenities to community through reciprocal agreements with other park districts 2007-2010 Agreement in place for use of Des Plaines driving range and golf courses.

Initiative: DIFFERENTIATE THROUGH EXCEPTIONAL CUSTOMER SERVICE
Item Status Initiative Target Date> Comments
6.1 * Identify and implement operating efficiencies 2007-2010 A list of cost savings and efficiencies was handed out at September Park Board Meeting.
6.2 * Provide a centrally managed, convenient, "customer friendly" registration, facility scheduling and membership purchasing operation 2007-2010 On-line registration for camp deposits; e-mail household numbers to past registrants each season for ease in registration and to avoid phone calls.
6.3 * Finalize and implement customer service standards and hold team members accountable 2007-2008 Draft of standards developed.
6.3A + Ensure that during core business hours, the main phone number at each facility will be answered by a "live" person 2007-2008 Implementation of new phone system allows for more flexibility.Live person is answering phones where practical.
6.4 * Develop a customer service employee team to identify and address recurring customer service issues, operational efficiencies, procedural recommendations, training opportunities, etc. 2007-2008 Customer Service Team has been developed, list of issues to be addressed has been developed. Team is meeting monthly to address issues.
6.5 + Implement updated emergency operating plans and train employees on them 2007-2008 Training has taken place at all facilities.
6.6 * Update all policy manuals, ordinance codes and training manuals to reflect current practices 2007-2009 Several groups of administrative policies have been sent to the Board and approved.
6.6A + Update and publish Park Ordinance Code Book 2007-2008 Distributed to staff, police, fire and school districts.
6.6B * Review and update Administrative Policy Manual 2009-2010 Several groups of administrative policies have been sent to the Park Board and approved
6.6 C = Review and update Full Time & Part Time Personnel Guidelines 2008-2009  
6.7 * Develop a customer service staff recognition program for above and beyond service 2009-2010  
6.8 = Implement practices such as hiring bi-lingual employees and conducting diversity training, that allow for better communication and service to non-English speaking customers 2009-2010  
6.9 + Develop and conduct random surveys of customer satisfaction and needs, analyze results and communicate for future improvement opportunities 2007-2008 Reports on outdoor pools, golf courses, and camps are complete for 2007. Plans are underway for distributing surveys in 2009.

Initiative: UPGRADE TECHNOLOGY
Item Status Initiative Target Date Comments
7.1 * Maximize use of technology to improve the management and dissemination of timely and reliable information (e.g., electronic bulletin boards, e-newsletters, etc.). 2007-2010 Implemented new websites, e-newsletters, increased use of Rec Trac for reporting and Intranet being developed
7.1A   Explore and implement document management system 2009-2010  
7.1B * Evaluate and recommend Time & Attendance system. 2007-2008 Meeting with vendors and seeing demos.
7.1C + Evaluate and recommend Program Registration software (Webtrac, Maintrac). 2007-2008 Decision reached to remain with Rec Trac through 2010. Will be revisited in next strategic plan.
7.1D = Implement Time & Attendance software recommendation 2008-2009  
7.1E + Implement Program Registration software recommendation 2007-2009 Item is for next strategic plan.
7.1F + Upgrade to Exchange 2007 2007-2008  
7.1G = Max Ice (evaluate and recommend ice scheduling software) 2008-2009  
7.1H = MSI (evaluated and recommend general ledger, accounts payable and payroll software) 2008-2009  
7.1I + Fore Reservations (evaluate and recommend golf software) 2008-2009 Software is meeting current needs--no change recommended at this time.
7.1J + Upgrade Maintrac software 2007-2008  
7.1K + Implement Park Services on upgraded Maintrac 2007-2008 System upgrade is completed; VSI was on site to assist in implementation and conduct training.
7.1L * Implement Park Center on upgraded Maintrac 2007-2008 Park Center participated in training and implementation meeting with VSI and will implement at the end of pool season.
7.2 * Increase ability to quickly deliver new functionality and/or systems in response to business needs ( i.e., debit card processing, work request systems etc.)   Implemented Get- it cards; generated e-mail program registration reminders to previous registrants.
7.2A * Implement a district-wide work request system 2007-2008 Reviewing Maintrac and Sharepoint Services
7.2B + Expand use of pass management system where it may apply 2007-2008 Fitness memberships, group exercise passes, tennis memberships, Splash Landings & Outdoor pool memberships and public skating passes are all on the pass management system. No other operations are applicable at this time.
7.2C * Implement district-wide gift card / debit card system. 2007-2008 Debit card available for outdoor pools summer 2007 & 2008; GPD gift card is being researched.
7.2D + Expand use of pass management system where it may apply 2007-2008 Pass management is being used at Fitness, Pools and Ice. No other uses are practical at this time.
7.3 + Provide a flexible infrastructure capable of supporting employee in a location neutral workforce and provide Internet access for customers ( i.e. WI-FI hotspots, 24/7 access). 2007-2008 Employees have access to e mail from home. Specified employees have ability for remote access to the park district network. Wi Fi access is available at Park Center and Ice Center.
7.3A + Implement patron use of personal wireless devices and, if feasible, implement at Park Center and Administration Building. 2007-2008 Wi Fi access is installed at Park Center and available for public use.
7.3B + Identify other Wi Fi sites and implement 2007-2008 Wi Fi installed at Ice Center and available for public use.
7.4 + Implement a single district wide phone system with unified messaging. 2007-2008 Implementation - December 2007
7.5 + Use third party consultant to assist in development of technology plan 2007-2008 Consultant reviewed overall plan and involved in phone system evaluation.
7.6 + Consolidate the management of all initiatives such as mobile phones, copiers, fax, and video surveillance equipment into Information Technology Dept. 2009-2010  
7.6A * Implement and evaluate security cameras at specified locations 2008-2009 Cameras have been installed at Glenview Ice Center.
7.6B * Evaluated, recommend and implement changes to existing cell phone services 2007-2008 Changes being made as contracts expire.
7.6C + Implement use of PDA/Smart phones for key staff 2007-2008 Executive Director, Division Superintendents and management staff at Park Center have Smart phones.
7.7 = Implement use of intranet to enhance internal communications, operating efficiencies 2008-2009  
7.8 * Maximize the use of electronic data to enhance trend reporting, analysis and setting benchmarks (registrations, attendance, etc.) 2008-2009 Developing Attitude and Interest Survey that will allow benchmarking to other like communities
7.9 + Foster a high level of confidence in the reliability and stability of park district systems 2007-2008 Ongoing project but 2007-2008 initiatives have been completed- Computer hub moved to Park Center to use generator backup if necessary.
7.9A + Centralize server and network hardware 2007-2008 Completed the move of computer hub to Park Center.
7.9B + Implement data back-up using DSL/cable 2007-2008  
7.10
*
Restructure file management system and improve file security. 2007-2008 Restructuring of Park Center file directories is complete.

Initiative: IMPROVE INTERNAL COMMUNICATION
Item Status Initiative Target Date Comments
8.1 * Create universal standards for effective communication: templates to ensure a consistent message and reliable information are being communicated (voicemail greeting, email signature lines, memo format, meeting agendas, etc.). 2007-2008 Marketing templates have been created for press releases, media alerts, bios.
8.2 * Establish regularly scheduled meetings and training sessions for all levels of staff to foster top-down and bottom-up communication. 2007-2010 Ongoing
8.2A + Implement semi-annual all FT staff meetings 2007-2008 Three meetings have been held.
8.2B * Implement quarterly supervisor / manager meetings 2007-2008 Fast Track Computer Training, Simon Bailey Customer Service, Environmental Training and Team Training.
8.2C * Implement quarterly breakfast with Executive Director 2008-2009 Structure for the meetings (participant selections, questions, etc.) is in development.
8.3 + Implement an annual employee opinion survey (year round and seasonal employees), analyze & communicate results, implement changes as necessary. 2007-2008 Surveys completed for 2007 and 2008.
8.4 * Create and delivers a bi-monthly electronic newsletter targeted toward all employees, volunteers and independent contractors (instructors, etc.) and key partners. 2008-2009 Weekly Keeping You Informed and Quarterly newsletter are distributed to staff.
8.5 * Flow-chart current business processes to increase cross-functional communication and use as a baseline for any future operational or organizational changes 2009-2010 Workers comp process and preschool payment plan processes have been documented and process improvements made.
8.6 + Establish a team to help facilitate communication and team building through regularly scheduled professional and social internal events. 2007-2008 "Fun Team" is in place, events are being planned and carried out.
8.7 * Develop and implement a new commissioner orientation program. 2007-2008 Various one on one sessions have taken place to provide training and background information.

Initiative: BROADEN AND ELEVATE MARKETING EFFORTS
Item Status Initiative Target Date Comments
9.1 * Develop and implement a Glenview Park District branding strategy that includes a tag line, consistent look and feel for materials, signage and logo 2007-2008 Processes, procedures and standardization for marketing pieces has been implemented. Conducted focus groups to help develop strategy.
9.2 * Develop/update annual marketing plans and marketing campaigns that are based on business plans with measurable goals for each major facility/program area 2007-2008 Ice center, outdoor pools and both golf course plans are complete.
9.2A * Re-evaluate all current and future public information pieces based on their effectiveness in reaching target markets and meeting defined marketing communication objectives. 2008-2009 Have updated Park Brochure, various facility marketing pieces and website.
9.3 + Create a dynamic results-oriented marketing department 2007-2008 Ongoing - marketing director hired; implemented increased use of market research, realigned staff responsibilities.
9.3A + Explore new marketing opportunities 2007-2010 Developed new marketing efforts with Glen Town Center and North Shore Tourism Bureau; LaSalle Bank promotion with Glenview National 9; implemented integrated marketing campaigns to increase public awareness through multiple meda outlets; developed joint hockey brochure with Stars.
9.4 + Increase the use of the Internet as a marketing tool including e-brochures, forms, community e-newsletter and regular website updates 2007-2010 E-newsletters, e-mail blasts, online surveys, online registration forms and regular website updates have all been implemented.
9.5 * Develop a Sponsorship/Advertising strategy 2009-2010 Being assigned as an intern project to work with all areas of park district
9.6 + Increase marketing research to reach target markets including use of internal data, community surveys, customer surveys, demographic data and focus groups 2007-2008 Outdoor pools, golf courses and camp reports completed and utilizing external research for planning.
9.7 = Develop a marketing campaign targeted toward businesses to generate sports league participation, golf/tennis lessons for business execs, holiday party and meeting facility rentals, company outings 2009-2010  

Initiative: EMPLOYER OF CHOICE
Item Status Initiative Target Date Comments
10.1 + Develop a recruitment, screening, and training program for all new employees. 2007-2008 Formal summer recruitment program is in place.
10.1A + Recruitment - Develop a database of local area high schools & colleges for communicating job opportunities. 2007-2008 Data base created- recruiting booths set up in local schools.
10.1B + Recruitment - Flow chart hiring process for FT, PT and seasonal employees and make recommendations for improvement 2007-2008 Process developed and documented and available on shared computer drive.
10.1C * Screening - Formalize process for ISP criminal background checks 2007-2008 Criminal background checks are completed on all new employees. Process for volunteers was approved by Park Board in Sept. 08.
10.1D * Screening - Investigate & analyze time and cost associated with nationwide criminal background checks for all employees. 2007-2008 Potential vendors have been identified. Currently conducting cost analysis.
10.1E * Screening - Investigate & analyze time, cost, and legal issues associated with general aptitude and personality testing for all employees. 2007-2008 Implemented pilot program for pre-employment testing.
10.1F * Screening - Establish process for conducting pre-employment reference checks and employment verification for all employees. 2007-2008 Pre-employment reference checking is taking place.
10.1G + Screening - Establish process for conducting education verification for all employees. 2007-2008 Consideration was given but not cost or time effective at this time.
10.1H * Training - Develop/Update new hire orientation for FT, PT, and Seasonal employees. 2007-2008 New hire full time employees have participated in a multiple session orientation.
10.1I + Training - Develop/Update benefits orientation for FT & PT-IMRF employees. 2007-2008 Power Point presentation developed and presented to new hires.
10.1J * Training - Develop process/schedules to allow all employees to attend new hire orientation and mandatory safety/awareness training programs 2008-2009 Date changed from 2007-2008. New Employee training with Executive Director implemented with all Full Time employees.
10.2 * Plan, develop and conduct ongoing developmental training in common critical areas. 2007-2010 Ongoing- Team training classes scheduled; Outlook training session conducted.
10.2A * Customer Service - Develop training plan for Customer Service Training and implement 2007-2008 Simon Bailey workshop conducted and another district wide program being developed for Feb. 09
10.2B * Information Technology - Develop IT core curriculum and implement 2007-2008 Ongoing-Conducted in house training on the use of Outlook and basic Excel
10.2C = Marketing - Develop training plan for marketing and communications and implement 2007-2008  
10.2D + Human Resources - Topics including Performance Management, FMLA, ADA. 2007-2008 All supervisors attend PDRMA-sponsored three day seminar on a variety of HR topics including the topics shown
10.2E + Disability Awareness - Develop training plan for disability awareness and implement. 2007-2008 Worked with NSSRA on updating their policy and procedure manual. Training was held for supervisory staff.
10.3 + Plan, develop, and implement regular function-specific training for business and IT professionals, senior staff, and other specialists 2007-2008 Participation in outside training has increased.
10.4 + Conduct a comprehensive survey to assure fair and competitive wages and benefits. 2007-2008 Watson Wyatt compensation survey complete and recommendation implemented.
10.5 + Create a state-of-the-art college internship program 2008-2009 Have hosted two recreation interns, IT intern and Marketing intern. Formal internship information packets are being updated.
10.6 * Refine the employee performance appraisal process for all classifications (Full-time, part-time, seasonal, introductory. 2008-2009 Division superintendent forms have been updated.
10.7 + Create a district-wide part-time volunteer coordinator position to expand and efficiently manage volunteer resources and recognition. 2009-2010 Volunteer coordinator position is in place and filled.
10.8 + Conduct annual benefits fair. 2009 Benefits Fair held in 2007 and 2008. Future plans are to conduct benefit fairs every other year and initiate wellness fairs.

 

 

Last updated 10/29/2008.
 
 